Change orders
Work outside the original scope. Approving one is the only thing that changes your budget.
Waiting for a decision
Approving adds the cost to your current budget. Rejecting leaves everything as it is.
- Under review
CO-004
Additional footing depth at the north elevation
Extend the north footing an additional 18 inches to reach bearing below the rock shelf.
Why: Rock encountered at four feet; the excavator could not advance.
- Cost impact
- +$12,500
- Schedule impact
- +3 days
- Budget if approved
- $1,300,900
Your current budget is $1,288,400 and has not changed.
Raised by Priya Mehta · Jul 22, 2026 at 10:00 AM · Foundation
Only an owner can approve a change order — the one action that moves the budget.
Settled
CO-003
Upgraded waterproofing membrane
Approved+$38,400Approved by Odessa Whitfield — added to the budget.
CO-002
Relocate the media room low-voltage panel
RejectedRejected — the budget was not changed.