Every update recorded on this project, newest first.
July 23, 2026
Review requiredFemi Adeyemi · Yesterday · Great room, Kitchen
HVAC trunk lines progressing. Tile for the primary bath arrived and was checked against the order.
2 items completed1 problem8 photosJuly 21, 2026
ApprovedPriya Mehta · 3 days ago · Primary bath, Great room, Foundation
Rough-in continued across the second floor. The plumbing crew finished the primary bath and the electricians started pulling home runs. One problem worth watching at the north footing.
3 items completed2 problems14 photosJuly 18, 2026
ApprovedPriya Mehta · 6 days ago · Foundation, Garage
Foundation waterproofing completed on the south and east walls. Garage slab poured and finished.
4 items completed11 photosJuly 15, 2026
AmendedOdessa Whitfield · 1 week ago · Site
Utility trenching for the north side. Amended to correct the trade on site — excavation crew, not plumbing.
2 items completed1 problem6 photos