Lakeview Residence

Reports

Weekly summaries you can share, and a PDF of any approved update.

Weekly summaries

WEEK

Jul 13 – 19, 2026

Approved

Foundation wrapped up; rough-in underway across the second floor.

Waterproofing and the garage slab were completed early in the week, closing out the foundation phase. Plumbing and electrical rough-in began on the second floor and are progressing well. The main thing to watch is rock at the north footing, which surfaced late in the week and may need a change order.

Completed this week

  • Foundation waterproofing on the south and east walls
  • Garage slab poured and finished
  • Primary bath plumbing rough-in

Still in progress

  • Second-floor electrical
  • HVAC trunk lines

Priorities for next week

  • Decide on the steel beam location
  • Clear the rock at the north footing
  • Schedule the rough-in inspection

Approved by Odessa Whitfield on Jul 20, 2026 at 12:00 PM

Summaries are generated from your approved updates in the live app.

Daily update reports

Any approved update can be exported as a print-ready PDF.

  • July 21, 2026

  • July 18, 2026

  • July 15, 2026

The live app generates a branded, print-ready PDF. Start free to try it.